Nuclear bulletin

Nuclear Bulletin No. 2

Mirko Millefanti

Nuclear Bulletin No. 2

Versione italiana →

Faster permits, slower builds: Long Mott gets its permit, Darlington revisits schedule and cost. Nuclear Intelligence No. 2 (W45–W46), covering 2 – 15 November 2026.

In brief

  • In the United States, the NRC issues the construction permit for Long Mott's four Xe-100 units, the first for a high-temperature gas-cooled reactor in nearly 60 years, and narrows the role of its ACRS advisory committee to truly novel issues.
  • In Canada, OPG says the first BWRX-300 at Darlington will meet neither its October 2030 date nor its CAD7.7 billion estimate.
  • In France, the industry expects EUR185 billion of orders over ten years and more than 100,000 hires, two thirds of them at suppliers.
  • In Poland, IHI receives Westinghouse's order for the containment and the large CA01 module of the first AP1000; in Italy, Nuclitalia will present its technology short list to the government by December.

Global outlook

12 Nov

COP31: industry asks for nuclear in the "35 by 35" pledge

At COP31 in Turkey, the World Nuclear Association asked that the Presidency's pledge to raise electricity to 35% of final energy demand by 2035 acknowledge the role of nuclear, which the text does not specifically mention. Reactors under construction, 88 GWe and the highest level in 40 years, will largely come online by then, four of them in Turkey. According to WNA's World Nuclear Outlook, if government targets are met global capacity could reach 1,467 GWe by 2050, beyond the tripling goal. The declaration to triple nuclear capacity now has 39 signatories; six joined after COP30, Italy among them.

World Nuclear Association

12 Nov

Turkey: Candu Energy to study a possible multi-unit Candu plant

At COP31 in Antalya, Candu Energy, an AtkinsRéalis subsidiary, signed a Memorandum of Agreement with Turkey's state-owned TÜNAŞ for a feasibility study of a possible multi-unit Candu plant: it will assess the site, infrastructure, environmental and economic aspects and how the programme could be delivered in Turkey, developing local supply chains and domestic expertise. The study is expected to be completed by the end of 2027 and is the first step on a path leading to FEED, to support future investment decisions.

AtkinsRéalis

10 Nov

China: construction starts at San'ao 4

CGN poured first concrete for the nuclear island of San'ao unit 4 in Zhejiang, the official start of construction. The unit belongs to the project's second phase, which began with unit 3 in November 2025. Unit 1 entered commercial operation this year and fuel loading at unit 2 was completed in November; six Hualong One units are planned in all, producing 52.5 TWh a year for the Yangtze River Delta region.

NucNet

9 Nov

Chornobyl: EUR303 million to restore the New Safe Confinement

At the Paris donors' conference hosted by France, Ukraine and the EBRD, 14 countries and international organisations pledged EUR303 million to the EBRD-managed international fund to repair the New Safe Confinement, damaged by a drone on 14 February 2025. Further pledges are expected in the coming months; the full scale of the work will become clear as detailed engineering progresses.

EBRD

Europe in focus

12 Nov

France: EUR185 billion of orders and over 100,000 hires in ten years

GIFEN, the French nuclear industry association, has updated the sector's outlook: the seven main clients, including EDF, Framatome, Orano and Naval Group, expect EUR185 billion of investment over ten years, 20 billion more than a year ago. Between 10,000 and 13,000 hires a year are needed, over 100,000 in total, for the EPR2s, the fuel cycle and continued operation of the fleet. Two thirds of the hires will be made by suppliers, mostly SMEs; 60% concern blue-collar workers and technicians.

For quality professionals: with two thirds of the hires at suppliers, training and qualifying new staff becomes a quality-system issue for the supply chain's SMEs.

franceinfo

4 Nov

Poland: IHI to supply the containment and CA01 module of the first AP1000

Westinghouse has awarded IHI engineering and long-lead procurement for the containment vessel and the large CA01 module of unit 1 at Lubiatowo-Kopalino. The CA01, more than 26 × 29 × 23 metres and made of 47 sub-modules, houses the reactor vessel and steam generators. The order follows PEJ's go-ahead in October for long-lead purchasing; Westinghouse has already placed conditional orders with four Polish companies for the CA02, CA03, CA05 and CA20 modules.

For quality professionals: the supply chain of Poland's first AP1000 is taking shape before the construction contract: for suppliers, this is the time to qualify.

IHI · World Nuclear News

4 Nov

Belgium: State–ENGIE nuclear deal pushed back to 12 December

The Belgian State, ENGIE and Electrabel have moved to 12 December the target date for signing Heads of Terms on the possible State acquisition of the nuclear activities, provided for in the letter of intent of 29 April. The parties report progress but significant remaining differences, notably on valuation.

ENGIE

5 Nov

France: EUR40 million from the EU Innovation Fund for Calogena's first commercial SMR

Calogena, a Gorgé group subsidiary, has been awarded EUR40 million from the European Commission's Innovation Fund for the potential construction of its first commercial reactor, to supply district heating to Pierrelatte. The CAL30 is a 30 MWt light-water small modular reactor. According to the company, it is the first time EU funding awarded to an SMR directly supports the construction of a commercial facility.

Calogena

Italy

4 Nov

Nuclitalia: technology short list by December

Nuclitalia, owned by Enel (51%), Ansaldo Energia (39%) and Leonardo (10%), will present to the government by the end of the year a short list from which the technology of Italy's future reactors will be chosen, on mainly technical but also geopolitical criteria. Ansaldo Energia CEO Fabrizio Fabbri told Milano Finanza that, once the technology is chosen, Ansaldo Energia will handle the industrial side of construction and its nuclear division will supply technology, components and R&D.

For quality professionals: the choice of technology will set the reference design and therefore the codes and qualification requirements the Italian supply chain will have to meet.

Milano Finanza

Regulation and quality

9 Nov

NRC: first construction permit for a high-temperature gas-cooled reactor in nearly 60 years

The NRC has issued Long Mott Energy, a Dow subsidiary, a construction permit for four X-energy Xe-100 reactors at Seadrift, Texas, which will mainly supply industrial steam. It is the NRC's first approval of a multi-module advanced plant, of a pebble-bed core and of a design with online refuelling, and its first review of an HTGR under the Licensing Modernization Project framework; the review met its 18-month schedule. The permit does not authorise operation. Dow has not yet decided to invest: a preliminary investment decision is expected in 2027.

For quality professionals: the permit lets the supply chain for long-lead components and materials mature before the investment decision: for Xe-100 suppliers, this is the qualification window.

NRC press release · World Nuclear News

12 Nov

NRC: the ACRS will focus on novel issues

Through a direct final rule to be published in the Federal Register, the NRC focuses the reviews of its independent Advisory Committee on Reactor Safeguards on safety-significant issues: first-of-a-kind designs, "truly novel or noteworthy" technologies and emerging safety issues. The stated aim is to meet the licensing timelines set by Executive Order 14300 while keeping independent expert review.

NRC press release

12 Nov

United Kingdom: industry and ONR join forces to change the sector's culture

Answering the Chancellor's open letter that followed the 2025 nuclear regulatory review, UK industry and regulators sent their first joint reply, through the new Nuclear Industry CEO Forum led by ONR. Their commitments: moving from periodic reviews to continuous assurance, using digital tools and AI safely, streamlining engineering and safety processes to remove duplication, and earlier collaboration between industry and regulators. Without urgent reform, they warn, the country risks an energy security gap and escalating costs.

For quality professionals: the explicit targets are proceduralism and duplication: proportionality of quality systems to safety significance is back at the centre.

ONR

Innovation and technology

4 Nov

Urenco USA produces the first commercial cylinder of LEU+

Urenco USA has produced at Eunice, New Mexico, its first cylinder of uranium hexafluoride enriched to between 5% and 10% U-235 (LEU+): according to the company, the first commercial LEU+ production in the Western world. The NRC authorised the plant to enrich up to 10% in September 2025. The enrichment level reached has not been disclosed; the cylinder will ship with a first customer order in late spring 2027.

ANS Nuclear Newswire

6 Nov

China: construction starts on the Xuwei HTGR

CNNC poured first concrete for the nuclear island of Xuwei unit 3 (Lianyungang, Jiangsu), a Chilong One high-temperature gas-cooled reactor developed with Tsinghua University: a scaled-up version of the HTR-PM at Shidao Bay and, according to CNNC, the first commercial application of the technology. Coupled with two Hualong One units, the plant will supply electricity and superheated steam for industrial uses such as oil refining, desalination and steel production. Design, procurement and delivery of the HTGR's equipment and materials are entrusted to CNNC Energy Technology.

NucNet · World Nuclear News

12 Nov

Fusion: record private investment in the IAEA World Fusion Outlook

Presented at the third meeting of the World Fusion Energy Group in Vienna, the fourth edition of the IAEA's World Fusion Outlook records USD4.5 billion of new fusion funding between July 2025 and July 2026, a record, and more than USD530 million spent by private firms on suppliers in 2025. Fusion facilities counted rise from 134 in 2022 to 174. According to FusionX, a further USD80 billion of private capital is needed over 20 years to reach commercialisation.

ANS Nuclear Newswire

11 Nov

Oklo: Groves-1 test reactor cleared for operation

DOE has cleared the final operations hold point of Oklo's Groves Isotope Test Reactor (Groves-1) in Texas, which went critical in August, less than a year after groundbreaking, under DOE's Reactor Pilot Program: the first in the programme on private land. The reactor moves into its research, testing and training phase: it will be used to qualify staff for future plants, evaluate the reliability of control rod drive mechanisms and gather criticality and reactivity data.

For quality professionals: experimental criticality and reactivity data are material for validating the computer codes used in design.

Oklo

Market and industry

11 Nov

Canada: Darlington's first BWRX-300 will miss its date and budget

With its third-quarter results, OPG said Darlington New Nuclear Project unit 1 will meet neither its October 2030 commercial operation target nor the CAD7.7 billion estimate, which includes systems common to the four units. OPG attributes the delay and overrun to GE Vernova Hitachi's ongoing engineering for a first-of-a-kind SMR, with impacts on construction execution and supply chain performance. A new assessment of cost and schedule is under way.

For quality professionals: on a first-of-a-kind project with engineering not yet closed, design revision management and configuration control at suppliers are the points to watch.

NucNet

5 Nov

X-energy picks Fluor for the Cascade nuclear island

Fluor will provide engineering, design development, supply chain, estimating and project control services for the nuclear island of the Cascade Advanced Energy Facility, developed by Energy Northwest near Richland, Washington, with 80 MWe Xe-100 reactors, built in standardised four- or twelve-unit plants. It is the two companies' second nuclear island contract after the first Xe-100 project in Texas, aiming to cut cost and schedule by carrying learnings from one project to the next. The conventional island and plant integration are entrusted to Cascade Nuclear Partners (Kiewit, Black & Veatch, Aecon).

X-energy

5 Nov

Canada: CAD518.5 million in the federal budget for the nuclear supply chain

The 2026 federal budget provides CAD518.5 million over five years, from 2027-28, for nuclear research, supply chains, workforce and regulatory capacity. This includes 261 million to Natural Resources Canada for supply chains, R&D and research reactors, 127 million to Atomic Energy of Canada Limited and 131.1 million to the Canadian Nuclear Safety Commission to prepare for new projects and become the sole federal regulator for nuclear energy projects.

Government of Canada, Budget 2026

Nuclear Intelligence is 1000eng's nuclear bulletin, every two weeks, compiled from verified public sources linked to each item. The "For quality professionals" notes are 1000eng's editorial comments, not quotations from the sources.